Project Description

Project Manheim Bulk Earthworks Commencement February 2019
Location Altona North Completion April 2019
Client EMKC Developments Value $2 Million

Overview

Bitu-mill were successful on tendering to work on; Bulk earthworks project comprising of approximately 28,000m3 (solid) cut to fill as first stage of construction works. Bitu-mill also completed 5000m2 carpark as second stage of construction works

Scope

Construction of hardstand area

  • Clearing and grubbing of existing site trees and mulching
  • Removal of redundant shade cloth structure
  • Excavation of rock floaters and removal from site
  • Rectification of uncontrolled fill
  • Cut and fill of approximately 28,000m3 (solid) of site material to construct hardstand area for future use

Construction of carpark  

  • Stabilisation of subgrade
  • Construction of flexible pavement design comprising of fine crushed rock material and asphalt layers
  • Drainage with an impermeable geofabric layers to prevent seepage
  • Linemarking to facilitate carparking zones

Outcomes

  • Works completed to high quality with exceptional finishes and tidy sites

  • Win – win attitude at play with negotiation on future work scopes

  • Exceptionally satisfied customer resulting in the further opportunities

  • Over 4,230 man hours works, with zero LTI’s, great achievement for the work scope with heavy plant movement.